The licenses for line 3 of the aerial cable are completed, works are 44% complete

Work progress is around 44%

The Cable and Fátima stations, of the aerial cable line 3 project, can now begin to rise.

The Urban Curator’s Office number 2 delivered the construction licenses to the points of Fátima and El Cable, with which the construction process is now firm.

The other two, those of The Cámbulos and Universities, They already had the viability documents issued by Urban Curator 1 since last January, so today they already have greater progress in the foundations.

According to Infimanzales, the progress of the foundation of the Los Cámbulos station is 100% and that of Universities is 90%.

The progress of the entire project is around 44%. This is what some stations look like today.

* Cable Station

* Bollard in the Fátima sector

On Sunday there is a road closure

The Manizales Mobility Secretariat reported that, due to the works that are being carried out on line 3 of the aerial cable, this Sunday, May 19, from 6:00 am to 6:00 pm, a road closure will be carried out on race 27, exactly in the section of access to the universities along Paralela Avenue and 62nd Street.

The measurement is taken to allow work at the Caldas Hydroelectric Power Plant (Chec), since the clear area is needed for an electric suspension.

#Colombia

 
For Latest Updates Follow us on Google News
 

-

PREV Neiva, where youth unemployment dropped the most • La Nación
NEXT the shipwreck of the 11 million gold and silver coins