A new sweep was made Office of the Comptroller General of the Republic in it Ministry of Sport. After reporting fiscal findings for the loss of the venue for the 2027 Pan American Games, this Tuesday they announced that in several agreements they found Fiscal findings amounting to 31.493 billion pesos.

This time, the audit of the financial statements of the sports portfolio covered the period of 2023, in which the income statement, changes in equity, notes to the financial statements and budget information for that year were also reported.

“Among the findings detected in this financial audit, the largest amount was determined by the non-compliance with Inter-Administrative Agreement 1215 of 2023, by the contractor InTerritoryspecifically in the execution of the first payment for $25.874 milliondisbursed by the Ministry of Sport, by not legalizing the documentation that supports its execution,” explained the fiscal control entity managed by Carlos Hernan Rodriguez.

Bogota Sept 2022. Office of the Comptroller General of the Republic

Photo:Milton Diaz / The Time

This happened because, according to the Comptroller’s Office, the contractor did not comply with what was agreed in the agreement, as did the supervisors and officials, who did not have the opportunity to take action on the matter. This led to an impact on the holding of intercollegiate games for the period of last year.

“Likewise, human talent in territorial entities was affected as a result of repeated non-compliance in their payments. Based on the above, a patrimonial loss of $25,874,521,747 is determined,” the control entity announced.

Intercollegiate Games (Reference image).

Photo:Ministry of Sport Press

The second most valuable finding is that of irregularities in the Construction contract L-2023-0889 of November 14, 2023which was signed by the mayor of Sopó, Cundinamarca, with the Sopó27 Sports Consortium, with the aim of building an athletics track at the La Trinidad Recreation and Sports Complex in the municipality.

The agreement was reached within the framework of the inter-administrative agreement COID 916-2023which they had signed from Sopó with the Ministry of Sport. “The situation relates to amounts of works paid for without having been executed, for the contracts derived from the inter-administrative agreements 916, 922 and 937 of 2023, signed by the Ministry of Sport and the municipalities of Sopó, Bahía Solano and Consacá respectively,” they explained on Tuesday.

For this particular case, The audit revealed that there was a violation of the supervisory duties“which generates a decrease in the resources available for the project, as well as distrust on the part of the community of the aforementioned municipalities, regarding the use of public resources. The fact causes damage to the heritage

public for $5,104,170,772 and has alleged disciplinary and criminal incidents“.

Carlos Hernán Rodriguez

Photo:Cesar Melgarejo/ The Time

Finally, Other findings revealed low budget execution and inadequate justificationpayments for unexecuted works and poor quality of contracted works. “It should be noted that in the second half of 2024 the Comptroller’s Office will audit the contracts and agreements signed for the implementation of projects aimed at the realization of the XXII National and Paranational Games in the Coffee Region in 2023,” the statement concluded.

Carlos López – Justice Editorial – @CarlosL49 – [email protected]

Read other Justice articles:

 
For Latest Updates Follow us on Google News
 

-

PREV Fox Ranger, an essential collection for MTB
NEXT Fire devastates four industrial warehouses in eastern Spain