Why don’t they deliver mega works for emergencies in Nariño?

In the last quarter of 2020 The construction of the Comprehensive Center for Disaster Risk Management – ​​CEGIRD of Pasto was announced, department of Nariño. Its objective It is to concentrate the emergency organizations in the event of any eventuality.

The project cost a little more than $14 billion and was awarded on December 23, 2020, with an execution period that was later extended by another yes.

The new delivery date was July 10, 2023 and a budget addition of nearly $10 billion, meaning that in total about $24 was paid billion for the work that was finally delivered after several delays.

Although it was scheduled for July, the work was delivered three months later, that is, in October and from that moment, until today, the work has not been delivered. megawork and the emergency organizations that are on maximum alert these days, continue working improvisedly.

Although the contract was signed during the administration of Eduardo José González, the work was not delivered. Later in the administration of Javier Pava and Olmedo López, the completion of the work was completed but the official delivery was not made.