In the midst of the announcement made by the director of the Institute of Urban Development (IDU), Orlando Molano, about the early delivery of the 100th Street and Suba Avenue bridge, which was scheduled to be completed between May and June 2025, and that can now be put into operation in December of this year; There were several concerns that appeared from citizens that claim that a part of the bridge structure is “crooked.”
And according to the complaints of several citizens in It presents a curvature in the concrete plate that they classify as “abnormal” in this type of work.
When this wearing course is applied and the bridge is tensioned with the post-tensioned cables, it will level out more“, I note.
According to this same information, it is expected that the deviation in the shape of the bridge in the section that is about to be connected will be solved with the tensioning of the segments (structure that creates the union of the two sections of the bridge), the construction and installation of the New Jersey (specific side rails) and the formation of the rolling layer, as explained by the IDU.
“The surveying area of the audit has provided daily support to the surveyors designated by the contractor, With our own equipment, the structural information is lifted and reviewed before, during and after each concrete pour through the segments.”they detailed from the project audit.