Quebradablanca Tunnel: Progress of recovery through Coviandina

Quebradablanca Tunnel: Progress of recovery through Coviandina
Quebradablanca Tunnel: Progress of recovery through Coviandina

On December 26, the Quebradablanca tunnel suffered damage after the fire of a heavy-duty vehicle transporting gasoline, a highly explosive material.

Photo: ANI

Coviandina, the company in charge of the work on the Bogotá – Villavicencio highway, reported that the recovery efforts of the Quebradablanca tunnel They have reached 96% progress.

A month ago, the Government announced the transfer of resources from the ANI to the Invías, to begin priority attention to critical points, which required an investment of $33,000 million.

“At the same time, we are advancing in the contracting of works for $186,000 million, as well as in a package of 7 projects for which studies and designs will be contracted for $15,000 million,” said the Minister of Transportation, William Camargo, and added that they were transferring $234,000 million to address the identified points.

This progress has been achieved through a series of activities, the entity said, including the rehabilitation of the Bogotá false portal tunnel, the installation of steel in columns and foundation beams, and the installation of lighting, cameras and signage.

Likewise, footings and beams have been demolished, while the concrete shot with metal fiber and the metal defense are installed, and lighting, cameras and signage are installed.

On another front, the works at the critical site of the kilometer 69+350 They have advanced 80%, corresponding to the first of the four stages of the work being carried out at this point. Recently, the installation of the pneumatic concrete and electrowelded mesh was completed, along with the drilling and installation of anchor bolts.

These advances are part of Coviandina’s commitment to the Bogotá – Villavicencio corridor so that the road infrastructure can come into operation again.

However, it is also required that the National Government, through the You send, execute the work at the critical points for which you are responsible. This collaboration is essential to ensure that the road can be reopened safely and efficiently.

Precisely for this second road corridor, in the Pipiral sector, the Minister Camargo had pointed out the joint work of studies and designs, given its high complexity, which would be intervened in the periods from 2024 to 2026.

 
For Latest Updates Follow us on Google News
 

-

PREV Camila Polizzi promises prizes for every Chile goal in the Copa América
NEXT formations, schedule and where to see the return of La Roja to the National Stadium — Futuro Chile