After several days of unclear information, the steel Ternium He acknowledged having caused Spills of ferrous chloride and acidic water in its Churubusco plant, which resulted in the pollution of the Arroyo La Talaverna.
Through a brief statement, the company admitted that on April 17 there was a Spill in the Storage tanks of its pickled plant, located in that industrial zone.
From there to date, the steel said that the company’s brigades have been working on the protocols of prevention y containmentas well as in the cleaning of the channel.
“In compliance with our commitment to transparency and in follow -up to what we reported in our official channels last Friday, on April 17 there was a spill in the storage tanks of the regenerating plant of pick -up solution in Churubusco plant.”
In the same way, they explained that they are executing a plan permanente Until the activities of Remediation of the stream.
“For ternium this situation has absolute seriousness and total priority, therefore, we inform the community and the corresponding authorities immediately, activating the protocols for remediation, containment and cleanliness. Likewise, our brigades have been working uninterruptedly from the first moment in cleaning the La Talaverna stream,” they said.
Finally, they said they have been receiving state and federal authorities, to carry out the Inspections relevant and know whether or not they comply with environmental regulations in the matter.
“We are executing a permanent plan until they conclude the remediation activities of this stream. Also, since last Friday we have received both local and federal authorities for relevant inspections,” they concluded.
bimc