The reversal of the Northern Gasducta strategic work to bring gas to the north of the country from Vaca Muerta, It will be completed by next September according to official and private sources.

The gas will make it possible to supply Bolivia’s declining gas supply, which is no longer able to cover its own demand.

The only public work that the Government decided to prioritize is key to bringing gas to seven central and northern provinces.

The gas will be for domestic use but also to allow the generation of electricity by thermal power plants.

He Development Bank of Latin America lent Argentina US$540 million for the work that will allow the growing “unconventional” gas production of Vaca Muerta to be distributed from the Neuquén Basin.

This is a key work to promote the energy transition towards less polluting fuels.

The revision will send gas to the provinces of Santiago del Estero, Tucumán, Catamarca, Salta, Jujuy, La Rioja and Córdoba.

When it is completed, it will allow the shipment of about 16 million cubic meters per day.

The “reversal” already included the regular line welding of sections 2 and 3, the first 100 kilometers of the so-called “Federal Integration Gas Pipeline” – out of a total of 122 km – that extends from Tío Pujio to La Carlota, in Córdoba. , linking the Central-West and North Gas Pipelines.

To shorten work times, an automatic welding system was used (the same one applied in the GPNK) and 4,059 welds were already carried out in 41 days.

The work is progressing with the construction of the remaining 22 km of the Gas Pipeline, 62 kilometers of loops to the Northern Gas Pipeline at the height of Ferreyra and the City of Córdoba and the change of direction of 4 compressor plants, with a completion date for the works scheduled for end of August.”

Techint and Sacde completed those welding, but they have not yet collected them from the national State, which owes them about $14,000 million in May, which was covered with credit from commercial banks.

The total budget for the work is US$720 million, of which the US$540 million credit from the Latin American Bank covers three quarters.

 
For Latest Updates Follow us on Google News
 

-

PREV China condemns US arms sales to Taiwan and reminds that the island is “a red line”
NEXT ACCIDENTS IN CÓRDOBA | A stone truck leaves the road and is crossed on the A-4 at the height of the Arcángel