Stoppage of works with national financing in Santa Fe
Within the framework of the reactivation of public works in Santa Fe, after the agreement signed this Tuesday between Province and Nation, From the Construction Chamber they raised a series of concerns.
The situation in Santa Fe shows a contrast between works financed with national provincial funds and those that depend on national financing. According to Robert Pilattihonorary president of the Santa Fe Construction Chamber, “The Municipality has 14 stopped works“in this context.
Read more: Agreement for works: Nación will complete the expansion of the Assa plant and Santa Fe the lighting in the Circunvalación
Regarding the loss of jobs, in the metropolitan area of Santa Fe and its surroundings, before the reactivation of provincial works “Between 2,500 and 3,000 jobs were lost in the area“said Pilatti.
Consequently, despite the expectation raised by the new agreements between the Nation and the Province, for the sector “It’s going to be difficult to get back to normal.”.
Read more: One by one, the 25 works that are resumed in Santa Fe after the signing of the agreement between the Province and the Nation